Capital Improvements

Completed in early 2025, the Delhi Water Treatment Plant upgrades included a new 2-million gallon capacity prestressed concrete groundwater storage tank.
Estimated Budget: $11.4 Million

Currently under construction, Owens Elevated Storage Tank is located off of Hwy. 95 in the Camp Swift area. The EST will hold one million gallons of water and stand at 179′ tall.
Estimated budget: $5.6 million

Scheduled for completion in 2027, the Aqua WSC Operations Center is being built with the future in mind. As our staff and supply needs continue to grow, this new facility will provide the space and resources needed to better serve our members & staff for years to come.
Estimated Budget: $9.8 Million

Our M/HT plant is located just off of Hwy. 71 toward Smithville. To meet the growing demand in the area, we’re making major improvements to the facilities surrounding this iconic tower including: a new 500,000 gallon ground storage tank, a new water treatment facility and more!
Estimated Budget: $6 million

As part of our proactive approach to facility maintenance, Aqua WSC is undergoing key renovations at our Camp Swift site. The project included replacing the filter media, adding two new detention ponds, and repairing vital concrete structures.
Estimated Budget: $1.8 million

Situated right next to our main office, this development marks a significant step forward in accommodating the growth of our staff, members, and Board. We look forward to future member events in this building!
Estimated Budget: $1.4 million